Monday, July 27, 2020

Progress inspection of Pantaleon Estrella Bridge connecting Estrella St. in DPWH Inspection Sees Estrella-Pantaleon, Binondo-Intramuros Bridges Right on Track for December 2020, March 2021 completion

Post from dpwh.gov.ph

Progress inspection of Pantaleon Estrella Bridge connecting Estrella St. in DPWH Inspection Sees Estrella-Pantaleon, Binondo-Intramuros Bridges Right on Track for December 2020, March 2021 completion  Public Works and Highways Secretary Mark A. Villar assured that despite the lockdown due to COVID-19 which hampered construction activities, the implementation of Binondo-Intramuros Bridge and Estrella- Pantaleon Bridge is right on schedule.  Secretary Villar said that based on a report of Undersecretary for Unified Project Management Office (UPMO) Operations and Technical Services Emil K. Sadain, we are seeing December 2020 completion of Estrella-Pantaleon Bridge Project while Binondo-Intramuros Bridge Project is aimed for opening by March 2021.  Undersecretary Sadain together with Project Director Virgilio C. Castillo of UPMO Roads Management Cluster 1 inspected the two (2) mega bridge projects crossing Pasig River.  Estrella-Pantaleon Bridge Project is now 56 percent completed while Binondo-Intramuros Bridge Project is now 36 percent completed, said Undersecretary Sadain.  Pouring of foundation for abutment is continuously undertaken on Estrella-Pantaleon Bridge.  Also ongoing is the piling of works for the foundation of Binondo-Intramuros Bridge, Binondo side downramp. By September, the steel bridging frame for the main bridge will be installed.  Although we have other urgent projects during this time of pandemic, we want to ensure everyone that these bridge projects are being rushed for completion to serve the public, said Undersecretary Sadain.  When completed, these two (2) bridges will augment the 30 existing ones across Pasig River, Marikina River and Manggahan Floodway and will ease traffic along EDSA and other major roads in Metro Manila.
Image from Public Works and Highways Secretary Mark A. Villar

Public Works and Highways Secretary Mark A. Villar assured that despite the lockdown due to COVID-19 which hampered construction activities, the implementation of Binondo-Intramuros Bridge and Estrella- Pantaleon Bridge is right on schedule.

Secretary Villar said that based on a report of Undersecretary for Unified Project Management Office (UPMO) Operations and Technical Services Emil K. Sadain, we are seeing December 2020 completion of Estrella-Pantaleon Bridge Project while Binondo-Intramuros Bridge Project is aimed for opening by March 2021.

Undersecretary Sadain together with Project Director Virgilio C. Castillo of UPMO Roads Management Cluster 1 inspected the two (2) mega bridge projects crossing Pasig River.

Estrella-Pantaleon Bridge Project is now 56 percent completed while Binondo-Intramuros Bridge Project is now 36 percent completed, said Undersecretary Sadain.

Pouring of the foundation for abutment is continuously undertaken on Estrella-Pantaleon Bridge.

Also ongoing is the piling of works for the foundation of Binondo-Intramuros Bridge, Binondo side down ramp. By September, the steel bridging frame for the main bridge will be installed.

Although we have other urgent projects during this time of the pandemic, we want to ensure everyone that these bridge projects are being rushed for completion to serve the public, said Undersecretary Sadain.

When completed, these two (2) bridges will augment the 30 existing ones across Pasig River, Marikina River, and Manggahan Floodway and will ease traffic along EDSA and other major roads in Metro Manila.